15Fri
Cisco SJC18 Chamber Replacement
SJC18 · Overall project spanning 125 days. Black - Contractor Items | Blue - Client Items | Red - City/Agency/Consultant | Purple - Engineering
thru Nov 13
Approval
10-day approval phase.
thru Jun 1
Submit Proposal
Milestone: Submit Proposal (0 days).
All day
Notice of Award
Milestone: Notice of Award (0 days).
All day
SOW
Statement of Work. Duration: 1 day.
All day
18Mon
PO Issued
Purchase Order Issued. Duration: 9 days.
thru Jun 1
June 2026
2Tue
Design
Design phase. Duration: 35 days.
thru Jul 22
Subcontracts
Subcontracts. Duration: 3 days.
thru Jun 4
Files & Documents from Cisco
Receive files and documents from Cisco. Duration: 2 days. Client item.
thru Jun 3
5Fri
MEP BOD & Layout
MEP Basis of Design and Layout. Duration: 12 days.
thru Jun 22
23Tue
Review MEP BOD
Review MEP Basis of Design. Duration: 3 days. Client item.
thru Jun 25
26Fri
MEP Design
MEP Design. Duration: 15 days. Engineering item.
thru Jul 20
Structural Design
Structural Design. Duration: 15 days. Engineering item.
thru Jul 20
Submittals
Submittals phase. Duration: 20 days.
thru Jul 27
MEP Submittals
MEP Submittals. Duration: 10 days.
thru Jul 13
July 2026
14Tue
MEP Submittal Approval
MEP Submittal Approval. Duration: 10 days. Client item.
thru Jul 27
21Tue
Review Drawings
Review Drawings. Duration: 2 days. Client item.
thru Jul 22
23Thu
Permitting
Permitting phase. Duration: 42 days.
thru Sep 22
Permit Application
Permit Application. Duration: 30 days. City/Agency/Consultant item.
thru Sep 2
28Tue
Long Lead Items
Long Lead Items procurement. Duration: 45 days.
thru Sep 30
Pumps
Pumps procurement. Duration: 9 weeks.
thru Sep 30
Heat Exchanger
Heat Exchanger procurement. Duration: 9 weeks.
thru Sep 30
Chambers (Per RFP Schedule)
Chambers procurement per RFP Schedule. Duration: 37 days.
thru Sep 18
Breaker
Breaker procurement. Duration: 10 days.
thru Aug 10
September 2026
October 2026
5Mon
Construction
SJC18 · Construction phase. Duration: 30 days.
thru Nov 13
Lab 155
Lab 155, SJC18 · Lab 155 construction phase. Duration: 8 days.
thru Oct 14
Mobilization / Layout / Pre-work (Lab 155)
Lab 155, SJC18 · Mobilization, layout, and pre-work for Lab 155. Duration: 1 day.
All day
Disconnect Chamber Utilities (Lab 155)
Lab 155, SJC18 · Disconnect chamber utilities in Lab 155. Duration: 1 day.
All day
6Tue
Rig Out Chambers (Lab 155)
Lab 155, SJC18 · Rig out chambers in Lab 155. Duration: 1 day.
All day
7Wed
Install Overhead MEP (Lab 155)
Lab 155, SJC18 · Install overhead MEP in Lab 155. Duration: 2 days.
thru Oct 8
9Fri
Floor Patching (Lab 155)
Lab 155, SJC18 · Floor patching in Lab 155. Duration: 1 day.
All day
12Mon
Rig in Chambers (Lab 155)
Lab 155, SJC18 · Rig in new chambers in Lab 155. Duration: 1 day.
All day
13Tue
Anchor Chambers (Lab 155)
Lab 155, SJC18 · Anchor chambers in Lab 155. Duration: 1 day.
All day
Tie in Chamber Utilities (Lab 155)
Lab 155, SJC18 · Tie in chamber utilities in Lab 155. Duration: 1 day.
All day
14Wed
Final Clean / Misc. Items (Lab 155)
Lab 155, SJC18 · Final clean and miscellaneous items in Lab 155. Duration: 1 day.
All day
Lab 155 Substantially Complete
Lab 155, SJC18 · Milestone: Lab 155 Substantially Complete (0 days).
All day
15Thu
Lab 159
Lab 159, SJC18 · Lab 159 construction phase. Duration: 22 days.
thru Nov 13
Mobilization / Layout / Pre-work (Lab 159)
Lab 159, SJC18 · Mobilization, layout, and pre-work for Lab 159. Duration: 3 days.
thru Oct 19
20Tue
Disconnect Chamber Utilities (Lab 159)
Lab 159, SJC18 · Disconnect chamber utilities in Lab 159. Duration: 2 days.
thru Oct 21
22Thu
Rig Out Chambers (Lab 159)
Lab 159, SJC18 · Rig out chambers in Lab 159. Duration: 1 day.
All day
23Fri
Install Overhead MEP (Lab 159)
Lab 159, SJC18 · Install overhead MEP in Lab 159. Duration: 4 days.
thru Oct 28
29Thu
Floor Patching (Lab 159)
Lab 159, SJC18 · Floor patching in Lab 159. Duration: 2 days.
thru Oct 30
November 2026
2Mon
Install Heat Exchanger (Lab 159)
Lab 159, SJC18 · Install heat exchanger in Lab 159. Duration: 2 days.
thru Nov 3
4Wed
Rig in Chambers (Lab 159)
Lab 159, SJC18 · Rig in new chambers in Lab 159. Duration: 1 day.
All day
5Thu
Anchor Chambers (Lab 159)
Lab 159, SJC18 · Anchor chambers in Lab 159. Duration: 1 day.
All day
6Fri
Tie in Chamber Utilities (Lab 159)
Lab 159, SJC18 · Tie in chamber utilities in Lab 159. Duration: 3 days.
thru Nov 10
11Wed
Final Clean / Misc. Items (Lab 159)
Lab 159, SJC18 · Final clean and miscellaneous items in Lab 159. Duration: 1 day.
All day
12Thu
Final Inspections
SJC18 · Final Inspections. Duration: 2 days.
thru Nov 13
13Fri
Lab 159 Substantially Complete
Lab 159, SJC18 · Milestone: Lab 159 Substantially Complete (0 days).
All day